Moisture readings must be taken to assure that not more than 12% moisture content is in the plaster prior to the application of any coating.

Sherri Ford
Landscaper
In TheConstructor you can ask and answer questions and share your experience with others!
Moisture readings must be taken to assure that not more than 12% moisture content is in the plaster prior to the application of any coating.
The maximum moisture content is limited to 12% in plastered walls before painting or application of any coating.