The rate analysis varies from place to place & it depends on the cost of construction material as well as labor cost.
Roughly, we can say Ru. 134 per Cft. Required when PCC of 1:4:8 is used.
In TheConstructor you can ask and answer questions and share your experience with others!
The rate analysis varies from place to place & it depends on the cost of construction material as well as labor cost.
Roughly, we can say Ru. 134 per Cft. Required when PCC of 1:4:8 is used.
Hi, determination of labour and material quantity of any brickwork or masonry is called a rate analysis.
In simple words, rate analysis is a calculation of the stones per cubic feet. In this case, generally dressed stones are used.
2stones/feet^2
4stones/feet^3
Rates depend on local labours costing and availability of materials. Labour rates include the application of mortar, transportation of materials, stone dressing and fixing.